Twenty-first Day: May 16, 2008 [Friday]

Date: May 16, 2008 [Friday]

Morning

Time In: 8:00 AM

Time Out: 12:00 PM

Afternoon

Time In: 1:00 PM

Time Out: 7:00 PM

The whole day was filled with the following tasks:

  • Estimate of Grooving. This was sort of an edit of the estimate I did few days ago prior to the changes made by the design consultant. This was to make sure that there are no large errors made and also to check the estimated values. My work was checked by a Site Engineer which somehow coincides with my estimated value. The Senior Project Manager also instructed me to provide quantity of linear Scanwolf PVC Plastic Grooving material. The standard length is 2.40 m. I also provided a breakdown for the two sub-contractors who will be charged for the orders to be made. I was tasked to order the 800 pieces of black Scanwolf PVC Plastic Grooving which is 20 mm in diameter.
  • Actual Accomplishment Report on CHB Piling and Wall Plastering. As part of the weekly task, I had another inspection to get an update of the Concrete Hollow Blocks piling as well as the plastering of interior and exterior walls prior to the weekly update of the S-Curve.
  • CHB Piling Update. Another weekly routine, I did an inspection in the three buildings to provide an update on the layout with CHB piled already. I simply shade the additional portion on the layout in the office of the Senior Project Manager for the update.

Post a Comment