Twenty-Fourth Day: May 21, 2008 [Wednesday]

Date: May 21, 2008 [Wednesday]

Morning

Time In: 8:00 AM

Time Out: 12:00 PM

Afternoon

Time In: 1:00 PM

Time Out: 6:00 PM

The whole day was filled with the following tasks:

  • Inspection Building 2, Second Floor. I did an inspection of the rooms in the second floor of building 2 and observed that most of the rooms were not yet plastered. the windows were not yet plastered also and most rooms did not have air condition opening yet. Also, there weren’t any zocalo yet and most of the toilet and bathroom weren;t plastered yet.
  • Check Dimension and Elevation of Doors and Windows. Due to the mistake committed by the masonry workers which was the erroneous elevation of window in one of the rooms in the first level of building 2, I checked the dimension and the elevations of each of windows and doors in the second floor of building 2. I was also tasked to check the height of the doors of the rooms which has been installed with tiles already to make sure the workers installing the tiles followed correctly what was in the plan. The foreman of the electrical wirings consulted me as to the dimension of the windows and the air condition opening in order for them to place the wirings properly. I was able to provide him the layout of the window and the air condition opening which will be their basis.
  • Preparation of Concrete Pouring Request. I was tasked to prepare the Concrete Pouring Request for the Slab on Grade at Laundry Area along grid line G1 to G2 on the first floor of building 2 and the stairs along grid line G1 to G2 between building 2 and building 3 from ground floor to second floor. Each area needs 5 cubic meter of 4000 psi. class of concrete.

Post a Comment