Date: May 20, 2008 [Tuesday]
Morning
Time In: 8:00 AM
Time Out: 12:00 PM
Afternoon
Time In: 1:00 PM
Time Out: 6:00 PM
The whole day was filled with the following tasks:
The weekly meeting with all the sub-contractors involved started around 9:30 in the morning. The topic involved the different concerns from different sub-contractors. The Senior Project Manger acknowledged the masonry for having done well for the turned over rooms in the first level of both building 2 and building 3. However, he made mention of the reason why one room in building 2 was not yet turned over. I was able to reason out and explained and informed him that the rectification was on-going.
task:
- Preparation of Concrete Pouring Request. I was tasked to prepare the Concrete Pouring Request for the Second Lift of Potable Water Cistern Tank along grid line C to D from grid line 2 to 3, prior to the scheduled pouring of concrete later that day.